
OVERVIEW

SIZE
-
Generation capacity of 122 GW; 590 billion units produced (1 unit = 1kwh)
-
India has the fifth largest electricity generation capacity in the world
-
T & D network of 5.7 million circuit km – the 3rd largest in the
world
-
Coal fired plants constitute 57% of the installed generation capacity,
followed by 25% from hydel power, 10% gas based, 3% from nuclear energy and
5% from renewable sources
|
|

Over 150,000 MW of
Hydel Power is yet to
be tapped in India

India requires an additional
100,000 MW of generation
capacity by 2012
|
STRUCTURE
-
Majority of Generation, Transmission and Distribution capacities are with
either Public sector companies or with State Electricity Boards (SEBs)
-
Private sector participation is increasing especially in Generation and
Distribution
POLICY
|
|
|
-
Policy framework: Electricity Act 2003
and National Electricity Policy
2005
-
Incentives: Income tax holiday for a block of 10 years in the first 15
years of operation; waiver of capital goods import duties on mega power
projects (above 1,000 MW generation capacity)
-
Independent Regulators: Central Electricity Regulatory Commission for
central PSUs and inter-state issues. Each State has its own Electricity
Regulatory Commission.

•G - Generation •T - Transmission •D - Distribution
Source: Ministry of
Power, Capitaline

OPPORTUNITY

OUTLOOK
-
Over 90,000 MW of new generation
capacity is required in the next seven
years
-
Power costs need to be reduced from the
current high of 8-10 cents/unit by a
combination of lower AT & C losses, increased generation
efficiencies and added low cost generating
capacity
POTENTIAL
-
Large demand-supply gap: All India
average energy shortfall of 7% and peak
demand shortfall of 12%
-
The implementation of key reforms is
likely to foster growth in all segments:
-
Unbundling of vertically integrated SEBs
-
“Open Access” to transmission and
distribution network
-
Distribution circles to be privatised
-
Tariff reforms by regulatory authorities
-
Opportunities in Generation for:
-
Coal based plants at pithead or coastal
locations
(imported coal)
-
Natural Gas/CNG based turbines at load
centres or near gas terminals
-
Hydel power potential of 150,000 MW is
untapped as assessed by the Government of
India
-
Renovation, modernisation, up-rating and
life extension of old thermal and hydro
power plants
-
Opportunities in Transmission network
ventures - additional 60,000 circuit km of
transmission network expected by 2012
-
Opportunities in Distribution through
bidding for the privatisation of
distribution in thirteen states that have
unbundled/corporatised their State
Electricity Boards – expected to take
place over the next 2-3 years
-
Total investment opportunity of about US$
200 billion over a seven year horizon

For additional information: Ministry of
Power, Central Electricity Regulatory
Commission, State Electricity Regulatory
Commission (http://powermin.nic.in)
|